Completed OPWC Projects

OPWC 32C - Kolbe Road 

Week of 08/12/2019

South Kolbe Milling

005

North Kolbe Milling

001

Kolbe pavement repairs

010

Kolbe paving intermediate

004

Kolbe paving surface asphalt

008

OPWC 33A  - Currently Under Construction

Week of 9/30/2019

Rita Drive Removal and Replacement

025

Week of 9/23/2019

Drainage improvements.

258

Week of 9/16/2019

Casting Adjustments and Underdrain.

241

Week of 9/9/2019

Concrete prep work and paving. Field issues, storm and void under existing pavement.

288

Week of 9/2/2019

Concrete Prep work and paving.

178

Week of 8/26/2019

Concrete Paving and Asphalt Paving.

004

Week of 08/19/2019

Base repairs. Concrete removal for new concrete placement. New curb and gutter placement. Steel placement for 

001

Week of 08/12/2019

Base, water valve, and storm repairs. New concrete work.

016

Week of 07/29/2019

Concrete Work and Curb Ramp Removals and Replacements - Asphalt Roadways

077

Week of 07/22/2019

Milling of Asphalt Roadways

006

OPWC 33B - Complete

Complete Photos

Belmont After

Week of 11/04/2019

Curb and Gutter Removal on Fiesta

Week of 10/21/2019

Lemonwood Cul-De-Sac Pour

Week of 10/7/2019

Concrete removal and underdrain.

Lemonwood removal of NB lane

Week of 9/30/2019

Asphalt and Concrete Paving.

Lemonwood Pave 2

Week of 9/23/2019

Asphalt paving. Sidewalks. Curb and Gutter Installation.

Belmont Sidewalks

Week of 9/16/2019

Asphalt base repair

Belmont Base Repair II

Week of 9/9/2019

Asphalt milling various streets.

Belmont Milling

Project Schedule for OPWC 34 A and OPWC 34B

Detailed Project Schedule for OPWC 34A and OPWC 34B

OPWC 34Aopwc34amap Opens in new window

OPWC 34A Map

opwc34alist

Project Information:

Contractor: Terminal Ready Mix

Project Manager: Veronica A Newsome

Cost: $905,488.89 + 10% contingency.

Delayed Construction Start date: 08/23/21

OPWC 34B

opwc34bmap

OPWC 34 B East

OPWC 34A West

opwc34blist

Project Information:

Contractor: Terminal Ready Mix

Project Manager: Jessica S. Potter

Cost: $713,847.89 + 10% contingency.

Delayed Construction Start date: 08/23/21