Completed OPWC Projects

  • Ohio Public Works Commission (OPWC) Projects

    • OPWC 38 A&B - 2025 Construction 

                   OPWC 38 A and B Engineering Department List

In-house repairs:

Updated Inhouse Paving List 05232025

OPWC 37

  • 2024 Engineering Department contract work (work will be completed prior to November 1, 2024):

  • 2024 Street Department In-house Road Rehab Work (priority list as funding allows):2024 Street Department Paving List without PCI Scores

OPWC 37A

OPWC 37A Roadway Location Map

Project Information:

Contractor: D.L. Smith Concrete, LLC.

Project Manager: Jessica Potter

Cost: $1,224,172.68

Construction Start date: June 17th, 2024

Construction Completion date: October 17th, 2024

OPWC 37B

OPWC 37B Roadway Location Map

Project Information:

Contractor: Terminal Ready-Mix, Inc.

Project Manager: Jessica Potter

Cost: $1,243,411.18

Construction Start date: June 24th, 2024

Construction Completion date: August 7th, 2024

OPWC 36 A&B - 2023 Construction

OPWC 36A&B Schedule

OPWC Roadways to be Rehabilitated

36aandb

OPWC 36A

36a


Project Information:

Contractor: Terminal Ready Mix

Project Manager: Jessica S Potter

Cost: $1,033,683.355 + 10% contingency.

Construction Start date: May 30, 2023


OPWC 36B

36b


Project Information:

Contractor: Terminal Ready Mix

Project Manager: Jessica S. Potter

Cost: $529,369.90 + 10% contingency.

Delayed Construction Start date: May 30, 2023

OPWC 35A

opwc35image

opwc35astreets

Project Information:

Contractor: Fabrizi Trucking and Paving

Project Manager: Jessica Potter

Cost: $747,522.65 + 10% contingency.

Construction Year: 2022

OPWC 35B

opwc35bimage

opwc35bstreets

Project Information:

Contractor: Terminal Ready Mix

Project Manager: Jessica Potter

Cost: $1,037,352.00 + 10% contingency.

Construction Year: 2022

Project Schedule for OPWC 34 A and OPWC 34B

Detailed Project Schedule for OPWC 34A and OPWC 34B

OPWC 34Aopwc34amap Opens in new window

OPWC 34A Map

opwc34alist

Project Information:

Contractor: Terminal Ready Mix

Project Manager: Veronica A Newsome

Cost: $905,488.89 + 10% contingency.

Delayed Construction Start date: 08/23/21

OPWC 34B

opwc34bmap

OPWC 34 B East

OPWC 34A West

opwc34blist

Project Information:

Contractor: Terminal Ready Mix

Project Manager: Jessica S. Potter

Cost: $713,847.89 + 10% contingency.

Delayed Construction Start date: 08/23/21

OPWC 33A

Project Information:

Contractor: D.L. Smith

Project Manager: Veronica Newsome and Seth Schilling

Cost: $1,296,914.99

Construction Year: 2019

OPWC 33B

Project Information:

Contractor: D.L. Smith

Project Manager: Jessica Potter

Cost: $ TBA

Construction Year: 2019

OPWC 32C - Kolbe Road 

Project Information:

Contractor: Erie Blacktop, Inc.

Project Manager: Doug Hasel

Construction Year: 2018