- Home
- Government
- Departments
- Engineering
- Past Projects
- OPWC Projects
Completed OPWC Projects
OPWC 32C - Kolbe Road
Week of 08/12/2019
South Kolbe Milling
North Kolbe Milling
Kolbe pavement repairs
Kolbe paving intermediate
Kolbe paving surface asphalt
OPWC 33A - Currently Under Construction
Week of 9/30/2019
Rita Drive Removal and Replacement
Week of 9/23/2019
Drainage improvements.
Week of 9/16/2019
Casting Adjustments and Underdrain.
Week of 9/9/2019
Concrete prep work and paving. Field issues, storm and void under existing pavement.
Week of 9/2/2019
Concrete Prep work and paving.
Week of 8/26/2019
Concrete Paving and Asphalt Paving.
Week of 08/19/2019
Base repairs. Concrete removal for new concrete placement. New curb and gutter placement. Steel placement for
Week of 08/12/2019
Base, water valve, and storm repairs. New concrete work.
Week of 07/29/2019
Concrete Work and Curb Ramp Removals and Replacements - Asphalt Roadways
Week of 07/22/2019
Milling of Asphalt Roadways
OPWC 33B - Complete
Complete Photos
Week of 11/04/2019
Week of 10/21/2019
Week of 10/7/2019
Concrete removal and underdrain.
Week of 9/30/2019
Asphalt and Concrete Paving.
Week of 9/23/2019
Asphalt paving. Sidewalks. Curb and Gutter Installation.
Week of 9/16/2019
Asphalt base repair
Week of 9/9/2019
Asphalt milling various streets.
Project Schedule for OPWC 34 A and OPWC 34B
Detailed Project Schedule for OPWC 34A and OPWC 34B
OPWC 34A
Project Information:
Contractor: Terminal Ready Mix
Project Manager: Veronica A Newsome
Cost: $905,488.89 + 10% contingency.
Delayed Construction Start date: 08/23/21
OPWC 34B
Project Information:
Contractor: Terminal Ready Mix
Project Manager: Jessica S. Potter
Cost: $713,847.89 + 10% contingency.
Delayed Construction Start date: 08/23/21