Columbia Gas Projects

Informative video for all gas line projects

Sharondale/ Leavitt Road Pipeline Replacement Project

Project Area:

sharondaleleavittmap

Project Work Schedule:

Project should formally begin February 2023 and last 2 to 3 months. 

UPDATE: 4/24/2023

Starting Monday 4/24, crews are shifting to nights to work the four road crossings. Work will run from 7PM – 7AM Monday-Thursday for roughly the next three weeks. Thanks for your continued patience and understanding. As always, please stay connected with questions or concerns.

Project Scope:

Crews will be installing approximately 6,000 feet of new plastic pipe serving 40 residences on sections of Sharondale and Leavitt/SR58. Please see the project map attached. Also including the info packet those on the route will be receiving in the mail. 

Townhall with Columbia Gas: 

Tuesday, January 24, 2023 @5:30 PM 

Project Questions:

  • Schedule a neighborhood or one-on-one meeting with us. Contact Benjamin Cutler at 216.215.4103.
  •  Review the Frequently Asked Questions. Informational Mailer
  •  Look for door hangers that may be placed on your front door with additional updates.
  •  Talk with members of the Columbia Gas team on site during the project.
  •  Follow Columbia Gas on Twitter and Facebook for project updates.

King Avenue Pipeline Replacement Project

Project Area:

KingAveMap

Project Work Schedule:

Preconstruction camera work is currently underway as of 03/16/2023 and the project should formally begin with mainline installation soon after, approximately Early April 2023. Work has paused until early 2024. Columbia gas is trying to get though as many hard surface repairs prior to the end of the year. Work has resumed 2/26/2024. Permanent restoration will progress into the spring of 2024.

Project Scope:

Crews will be installing approximately 8,000 feet of new plastic pipe serving 180 residences on sections of Lakeview, 11th, 12th, Parkview, Mildred, Osborn and Allison. Please see the project map attached. Also including the info packet those on the route will be receiving in the mail. 

Townhall with Columbia Gas: 

Thursday, March 23, 2023 @5:30 PM 

Project Questions:

  • Schedule a neighborhood or one-on-one meeting with us. Contact Benjamin Cutler at 216.215.4103.
  •  Review the Frequently Asked Questions. Informational Mailer
  •  Look for door hangers that may be placed on your front door with additional updates.
  •  Talk with members of the Columbia Gas team on site during the project.
  •  Follow Columbia Gas on Twitter and Facebook for project updates.

Lorain Eagle Avenue Pipeline Replacement Project

Project Area:

eagle ave

Project Work Schedule:

Preconstruction camera work is currently underway as of 7/7/2022 and the project should formally begin with mainline installation soon after, approximately mid-July 2022. 

Project Scope:

Crews will be installing approximately 9,140 feet of new plastic pipe serving 133 residences on sections of 31st, Fulton, Victory, Eagle, Industrial, Factory and Plant. Please see the project map attached. Also including the info packet those on the route will be receiving in the mail. 

Townhall with Columbia Gas: 

Tuesday, July 19, 2022 @5:30 PM 

Project Questions:

  • Schedule a neighborhood or one-on-one meeting with us. Contact Benjamin Cutler at 216.215.4103.
  •  Review the Frequently Asked Questions. Informational Mailer
  •  Look for door hangers that may be placed on your front door with additional updates.
  •  Talk with members of the Columbia Gas team on site during the project.
  •  Follow Columbia Gas on Twitter and Facebook for project updates.

West 18th Street Pipeline Replacement Project

Project Area:

Project map

Project Work Schedule:

Preconstruction camera work will begin the week of September 13, 2021 and the project should formally begin with mainline installation soon after. 

Project Scope:

Installation of of new plastic pipe serving residences in the area generally bounded by Washington (west), Long (east), W. 14th (north) and W. 19th (south). Please see the project map attached along with the informational mailer everyone on the route should have already received.

Townhall with Columbia Gas: 

Tuesday, September 28 @5:30 PM 

Project Questions:

  • Schedule a neighborhood or one-on-one meeting with us. Contact Benjamin Cutler at 216.215.4103.
  •  Review the Frequently Asked Questions. Informational Mailer
  •  Look for door hangers that may be placed on your front door with additional updates.
  •  Talk with members of the Columbia Gas team on site during the project.
  •  Follow Columbia Gas on Twitter and Facebook for project updates.

Atlas Drive Pipeline Replacement Project

Project Area:

Atlas Dr. Map

Project Work Schedule:

Preconstruction camera work is just underway and the project should formally begin with mainline installation in late June or early July. 

Project Scope:

Installation of 13,000 feet of new plastic pipe serving roughly 320 residences in the area generally bounded by Nebraska (west), Day (east), Cleveland (north) and Garfield (south). Please see the project map attached along with the informational mailer everyone on the route should have already received.

Townhall with Columbia Gas: 

Monday, June 7 @5:30 PM and Tuesday, June 8 @1 PM

Project Questions:

  • Schedule a neighborhood or one-on-one meeting with us. Contact Benjamin Cutler at 216.215.4103.
  •  Review the Frequently Asked Questions. Informational Mailer
  •  Look for door hangers that may be placed on your front door with additional updates.
  •  Talk with members of the Columbia Gas team on site during the project.
  •  Follow Columbia Gas on Twitter and Facebook for project updates.

Toledo Avenue Pipeline Replacement Project

Project Area:

Project map


Project Work Schedule:

Preconstruction Camera work to begin 1/25/21. Construction to begin the week of March 1st, 2021 and end Summer 2021. Evening and weekend work may occur.

Townhall with Columbia Gas: 

Virtual meeting. Thursday, January 21 at 1 PM or 5:30 PM

Project Questions:

  • Schedule a neighborhood or one-on-one meeting with us. Contact Benjamin Cutler at 216.215.4103.
  •  Review the Frequently Asked Questions. Informational Mailer
  •  Look for door hangers that may be placed on your front door with additional updates.
  •  Talk with members of the Columbia Gas team on site during the project.
  •  Follow Columbia Gas on Twitter and Facebook for project updates.