OPWC Projects

Schedule Update, 11/18/2021:

Fri 11/18:

  • Topsoil n. side W. 35th and s. side Rosecrest
  • Fill-in centerline Redbud and W. 35th using #411’s and compacting
  • Removing MOT and temp mailboxes from all streets
  • King – cleanup, remove washout pits on W. 11th

 

The remaining work for this season is to perform joint sealing on Rosecrest and n. side W. 35th, which will occur as soon as weather permits.

 

The remaining work for Spring prior to 4/30/22 is:

  • S. side W. 35th
  • S. side Redbud
  • Signs and pavement markings
  • Hydroseeding
    • N. side G
    • E. side King
    • Rosecrest
    • Redbud
    • W. 35th
  • Punchlist work

Project Schedule for OPWC 34 A and OPWC 34B

Detailed Project Schedule for OPWC 34A and OPWC 34B

OPWC 34Aopwc34amap Opens in new window

OPWC 34A Map

opwc34alist

Project Information:

Contractor: Terminal Ready Mix

Project Manager: Veronica A Newsome

Cost: $905,488.89 + 10% contingency.

Delayed Construction Start date: 08/23/21

OPWC 34B

opwc34bmap

OPWC 34 B East

OPWC 34A West

opwc34blist

Project Information:

Contractor: Terminal Ready Mix

Project Manager: Jessica S. Potter

Cost: $713,847.89 + 10% contingency.

Delayed Construction Start date: 08/23/21