Completed 2019 CDBG Funded Roadway Projects

Livingston/W.10th/E.34th Street Project

Project Before, During, and After PDF

Week of May 13th, 2019

  • Walks, W. 10th St.
  • Paving, W. 10th St.
  • Paving, E. 34th St.
  • Restoration, Livingston

10th St. Paving

Week of April 29, 2019

  • Paving, W. 10th St.
  • Paving, E. 34th St
  • Apron Replacement, Livingston Ave.

10th St. Paving

Week of April 22, 2019

  • Base Repairs, E. 34th St.

E. 34th St, Base Repair1

Week of April 15, 2019

  • West Side Poured, Livingston Ave.
  • West Side Steel Placed, Livingston Ave.
  • Intersection Base Repair, E. 34th St.

Livingston, West Side Poured

Week of April 8, 2019

  • Base Repair, E. 34th St.
  • Removed East Side, Livingston Ave.
  • New ADA ramps, W. 10th St.

E. 34TH BASE REPAIR

Week of April 1, 2019

  • East Side Poured, Livingston Ave.
  • Milled Asphalt, W.10th St.
  • Removed Base, E.34th St.

Livingston. poured east side of the street