Schedule Update, 03/31/2022:
Project Schedule for OPWC 34 A and OPWC 34B
Detailed Project Schedule for OPWC 34A and OPWC 34B
OPWC 34A
OPWC 34A Map

Project Information:
Contractor: Terminal Ready Mix
Project Manager: Veronica A Newsome
Cost: $905,488.89 + 10% contingency.
Delayed Construction Start date: 08/23/21
OPWC 34B

OPWC 34 B East
OPWC 34A West

Project Information:
Contractor: Terminal Ready Mix
Project Manager: Jessica S. Potter
Cost: $713,847.89 + 10% contingency.
Delayed Construction Start date: 08/23/21
OPWC 35A

OPWC 35A Map

Project Information:
Contractor: Fabrizi Trucking and Paving
Project Manager: Jessica S Potter
Cost: $747,522.65 + 10% contingency.
Construction Start date: Spring 2022
OPWC 35B

OPWC 35B Map

Project Information:
Contractor: Terminal Ready Mix
Project Manager: Jessica S. Potter
Cost: $1,050,651.41 + 10% contingency.
Delayed Construction Start date: Spring 2022